| Good Hope School Block two completion Budget | ||||||||
| Ugandan | ||||||||
| Finishing | Shillings | |||||||
| Windows | 50 | 70,000 | 3,500,000 | |||||
| Doors | 15 | 100,000 | 15.000,000 | |||||
| Paint | 2.400,000 | |||||||
| Solar pow | 5,000,000 | |||||||
| Labour | 2.000,000 | |||||||
| 27,900,000 | ||||||||
| Others | ||||||||
| Seats | 150 | 15,000 | 2,250,000 | |||||
| reference | 1,500,000 | |||||||
| Beddings | 8,000,000 | |||||||
| Games fac | 3,000,000 | |||||||
| 14,750,000 | ||||||||
| Land expansion valued at 5,000,000 Ug Shillings | ||||||||
| 42,650,000 | 22,000 US Dollars | |||||||