PRESUPUESTO GENERAL
PROYECTO: CONSTRUCCIÓN SISTEMA DE AGUA POTABLE COMUNIDAD "GUARANGUAY" (AYANGO)EL CHACO
UBICACION: COMUNIDAD DE GUARANGUAY (YANGO)  PLAZO 
PROYECTISTA :  "OPERASION AGUA" EQUIPO TECNICO REFERENCIAL
85 DIAS
ITEM  DESCRIPCION UNID CANTIDAD PRECIO COSTO
UNITARIO TOTAL
OBRA DE TOMA        
1 INSTALACION DE FAENAS Glb 1.00 638.24 638.24
2 REPLANTEO DE OBRA DE TOMA M2 8.00 2.75 22.00
3 EXCAVACION MANUAL TERRENO SEMIDURO M3 7.60 0.00 0.00
4 FUNDACION DE HºCº TIPO "B" 50% P.D.  M3 4.00 320.00 1,280.00
5 ELEVACIONES DE HºCº "TIPO B" CON 50% P.D M3 4.26 380.00 1,619.71
6 REVOQUE EXT. DE CEMENTO SOBRE HORMIGON M2 17.32 63.74 1,103.72
7 REVOQUE DE MORTERO CON SIKA - 1 (1:5 E=2,5 CM) M2 10.30 79.29 816.75
8 RECUBRIMIENTO IMPERMEABLE M2 10.30 79.13 815.10
9 PROV. Y COLOC. GRAVA PARA PRE FILTRO (1 - 1,5 M)  M3 4.32 159.45 688.82
10 CAMARA COLECTORA 0,6X0,6X0,75M PZA 1.00 894.18 894.18
11 CAMARA DE VALVULAS DE HºCº 0,4X0,4X0,5M  PZA 1.00 530.82 530.82
12 PROV. Y COLOC. ACCESO. OBRA DE TOMA GLB 1.00 850.34 850.34
LINEA DE ADUCCION        
13 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 3000.00 0.39 1170.00
14 EXCAVACION ZANJAS SUELO SEMIDURO M3 569.80 0.00 0.00
15 EXCAVACION DE 0-2M SUELO DURO M3 244.2 0.00 0.00
16 PROV. Y COLOC. TUBERIA PVC D=2" CLASE 15 (ESP- CAMP) ML 3000.00 22.66 67980.00
17 RELLENO MANUAL C/TIERRA CERNIDA (NO INCL.MATERIAL) M3 325.60 25.89 8429.78
18 RELLENO Y COMPACTADO MANUAL C/TIERRA COMUN M3 488.40 13.51 6598.28
19 PRUEBA HIDRAULICA - TUBERIA DE 1/2" HASTA 4" ML 3000.00 0.31 930.00
20 DESINFECCION DE TUBERIAS (HASTA 4") ML 3000.00 0.25 750.00
TANQUE DE ALMACENAMIENTO        
21 REPLANTEO DE ESTRUCTURAS Y EDIFICACIONES M2 5.70 3.97 22.63
22 EXCAVACION DE 0-2M SUELO DURO M3 1.94 0.00 0.00
23 PISO DE CEMENTO + EMPEDRADO E=7CM TIPO "B" TANQUE M2 2.01 102.99 207.01
24 ACERA TIPO "B"+ EMPEDRADO E=5CM M2 3.30 75.16 248.03
25 HORMIGON DE FERROCEMENTO M3 2.19 6771.30 14857.59
26 HºAº PARA LOSA TAPA (TANQUE DE AGUA ) M3 0.03 1911.87 58.50
27 CAMARA DE VALVULAS DE HºCº 0,9X0,9X0,66M PZA 2.00 732.30 1464.60
28 CAMARA DE ENTRADA DE HºCº 0,5X0,51X0,5M PZA 2.00 530.82 1061.64
29 DESIFECCION DEL TANQUE (HIPOCLORITO AL 70%) M3 4.93 5.72 28.19
30 PINTURA LATEX - EXTERIOR  M2 17.88 44.59 797.10
31 PROV. Y COLOC. ACCESORIOS TANQUE D= 3/4" GLB 2.00 2338.52 4677.04
RED DE DISTRIBUCION        
32 REPLANTEO Y CONTROL DE LINEAS DE TUBERIA ML 2500 0.39 975.00
33 EXCAVACION ZANJAS SUELO SEMIDURO M3 2000 0.00 0.00
34 EXCAVACION DE 0-2M SUELO DURO M3 500.00 0.00 0.00
35 PROV. Y COLOC. TUBERIA PVC D=1" CLASE 15 (ESP- CAMP) ML 1000.00 16.58 16580.00
36 PROV. Y COLOC. TUBERIA PVC D=3/4" CLASE 15 (ESP- CAMP) ML 500.00 11.58 5790.00
37 PROV. Y COLOC. TUBERIA PVC D=1/2" CLASE 15 (ESP- CAMP) ML 1500 7.29 10935.00
38 PRUEBA HIDRAULICA - TUBERIA DE 1/2" HASTA 4" ML 2500 0.31 775.00
39 DESINFECCION DE TUBERIAS (HASTA 4") ML 2500 0.25 625.00
40 RELLENO MANUAL C/TIERRA CERNIDA (NO INCL.MATERIAL) M3 2500 0.00 0.00
41 RELLENO Y COMPACTADO MANUAL C/TIERRA COMUN M3 2500 0.00 0.00
42 CAMARA ROMPE PRESION 0,6X0,6X0,6M PZA 1.00 1415.71 1415.71
43 PROV. Y COLOC. ACCESORIOS RED DE DISTRIBUCION GBL 1.00 192.48 192.48
PILETAS DOMICILIARIAS        
44 PEDESTALES PILETAS PUBLICAS M3 20.00 354.12 7082.40
45 CONEXIONES PILETAS PUBLICAS (6M PVC S/MEDIDO)  PZA 20.00 451.58 9031.60
ESTRUCTURAS ESPECIALES        
46 PASOS DE QUEBRADA L=6M D=3/4" PZA 7.00 1042.49 7297.43
47 PUENTE COLGANTE ACUEDUCTO L=20M PZA 5.00 3546.39 17731.95
CERCO MALLA OLIMPICA        
50 REPLANTEO CERCO PERIMETRAL M2 15.10 3.97 59.95
51 EXCAVACION DE 0-2M SUELO DURO M3 0.78 27.01 21.07
52 CIMIENTOS DE HºCº TIPO "B" 50% P.D. M3 0.78 402.43 313.90
53 SOBRE CIMIENTOS DE HºCº TIPO "B" 50% P.D. M3 0.42 602.40 250.60
54 PROV. Y COLOC. MALLA OLIMPICA ALAMB. Nº10 DE 3" M2 26.00 373.86 9720.36
55 PUERTA METALICA CON MALLA OLIMPICA  PZA 1.00 567.84 567.84
56 ALAMBRE DE PUAS ML 39.00 24.28 946.92
           
  COSTO TOTAL DEL PROYECTO (Bs)       208852.28 Bolivian Pesos
  COSTO TOTAL DEL PROYECTO (DOLARES AMERICANOS)       $29,582 US  Dollars
TECNICO PROYECTISTA